Section 1.3.7.2.11. Alternative-Analysis of Remaining Structure Subsequent to Load Path Failure
As indicated in 1.3.7.2.10, the designer may choose to depend
upon the depot level inspection instead of the walk-around visual. This would be a satisfactory alternative and
for this situation the assumption would be made that the major load path failed
between depot level inspections and that the aircraft would be designed to
operate safely with the failed load path until the next depot inspection. Figure 1.3.24
illustrates this case.
Figure
1.3.24. Illustration of Damage
Growth and Residual-Strength Guidelines for Remaining
Structure-Depot-Level-Inspectable